The electric bus tender: 900 buses, two bidders, one deadline missed

Documents obtained under the transparency law show the specification was revised twice after bids closed.

An electric bus charging at a depot
Photo: BytePress photo desk

The tender for 900 electric buses was issued in March, closed in May, and revised in June. The revisions narrowed the eligibility criteria by raising the minimum operating-history requirement.

The sequence

Our timeline is built from the tender documents, the two corrigenda and the minutes of three internal meetings. It is published in full with this story.

A specification that changes after bids are open is a specification written for somebody. — A former transport commissioner

What the corporation says

In a written response, the corporation said the revisions followed a technical review and were applied equally to both bidders.

What did you make of this story?

Tap once to react, tap again to take it back.

2 reactions from readers.

Reader Conversation

0 contributions

BytePress welcomes respectful, evidence-based dialogue. All submissions are moderated in accordance with our Community Standards.

Be the first to comment. Join the dialogue on this story; our editorial desk reviews submissions promptly.

Join the conversation

Public discourse · One comment a minute · Moderated
Never published. Used only to reach you about moderation or replies.